Site construction trailors

Status
Not open for further replies.
Construction trailers get feeders, they also are separate buildings or structures and require a grounding electrode system. See 250.32(A)
 
My take, correct me if I am wrong is if I run sevice entrance and not metal conduit I dont need sep equip ground. Just need grounding electrode at trailor.
 
My take, correct me if I am wrong is if I run service entrance and not metal conduit I dont need sep equip ground. Just need grounding electrode at trailor.

You can not run a 'service' from one building to another. Only feeders.

If you are under the 2005 or previous you may be able to take advantage of 250.32(B)(2).
 
Status
Not open for further replies.
Top