Greeting all,
I have one distribution system which contains.
1. Two generators one on duty and the other is standby
2. one Main Distribution panel Board
3. Two Sub distribution panel board
4. Eight Panel boards which are located in buildings
I have given grounding connection detail the figure exhibit 250.29 page-229 NEC-2008.
But I have received a comment to remove the main bonding jumper from this detail and it is only for source at generator point and it is not applicable for other panel boards and sub panels
Please advise me what to do.
best regards,
Hameedullah Ekhlas
Electrical Engineer
Kabul Afghanistan.
I have one distribution system which contains.
1. Two generators one on duty and the other is standby
2. one Main Distribution panel Board
3. Two Sub distribution panel board
4. Eight Panel boards which are located in buildings
I have given grounding connection detail the figure exhibit 250.29 page-229 NEC-2008.
But I have received a comment to remove the main bonding jumper from this detail and it is only for source at generator point and it is not applicable for other panel boards and sub panels
Please advise me what to do.
best regards,
Hameedullah Ekhlas
Electrical Engineer
Kabul Afghanistan.