Designing a addition to a house. The guy is changing the service of over-head to under ground because the new roof peak will be in the way.
Im making the new service underground to a meter, and a new panel (nema 3R) with 8 poles . Im going to feed the new addition from this panel, and then feed the existing panel.
My question basically is, can all the breakers for the new addition be located on the exterior in the 8 pole panel? (ie if a breaker tripped in this new addition, you would be walking outside to flip it back on)
Opinions are welcome, thanks.!
Im making the new service underground to a meter, and a new panel (nema 3R) with 8 poles . Im going to feed the new addition from this panel, and then feed the existing panel.
My question basically is, can all the breakers for the new addition be located on the exterior in the 8 pole panel? (ie if a breaker tripped in this new addition, you would be walking outside to flip it back on)
Opinions are welcome, thanks.!