blingbling4r
Member
- Location
- Seattle, WA
We got dinged by a code inspector just now saying we got to have our data rough in done in conduit. This is a new T.I. build out and all we did was just a mud ring and a string above the ceiling height. The inspector says according to 2008 code it has to have a raceway. Only time you can fish wire is in existing walls. 
He didn't cite us yet and will come back later today to re-inspect. What are your thoughts on this?
	
		
			
		
		
	
				
			He didn't cite us yet and will come back later today to re-inspect. What are your thoughts on this?
 
				
 
 
		 
 
		 
 
		