well i think POCO will run underground to meter at property line then we will trench to the house (400') and leave enough conductor to make it to house for permanent power. Should I just put a load center on a post with some receps?
I would install a panel there with the intention of it being permanent in anticipation of an electric gate or landscape lights at the front of the property.
Run your 2 1/2" conduit for your service conductors and a 1 1/2" conduit for temp power.
Pull in some 6/3 SER for your temp and pull it out when not needed and use it on the next job![]()