I have a residential job with a 400A service feeding two 200A main breakers in separate enclosures. Someone did a generator job on this service by installing a 200A Single Throw disconnect and feeding the load side of each breaker. To me it was always a given that double throw would be required. But I can not find it in the code, least not in the service part.
So my question is? where can I find in the code the part that deals with this? Another question is, if I change this to a double throw switch, fed from the meter then use three wire lugs ( I have to add another main disconnect) and feed the three mains from the disconnect does the disconnect has to be fusible? and if not I assume the tap rule applies from the load side of the disconnect to the mains. The meter, mains and disconnect are all grouped.
Thank you.
So my question is? where can I find in the code the part that deals with this? Another question is, if I change this to a double throw switch, fed from the meter then use three wire lugs ( I have to add another main disconnect) and feed the three mains from the disconnect does the disconnect has to be fusible? and if not I assume the tap rule applies from the load side of the disconnect to the mains. The meter, mains and disconnect are all grouped.
Thank you.