I am on a project where my superviser wants to route the 2 sets of feeders from the MDP on the outside of the building, nipple out the back of the MDP into a Panel on the back side, then us that panel as a pull box feeding 2 other panels right next to it. I didn't feel like this was a very good idea but couldn't find anything in the code book... any thoughts?
	
		
			
		
		
	
				
			 
				
 
 
		 
 
		