The last job I worked on,this plant has 40 to 50,000 feet of cable tray,some areas with 3 levels of tray - 6 trays wide,,plant is still under construction.Substation is elevated and all cable enters gear from below.
The large xfmr is 13.8 / 4160,the smaller 4 of them is 4160 / 480.There is 2 more located remote from substation
dick
	
		
			
		
		
	
				
			The large xfmr is 13.8 / 4160,the smaller 4 of them is 4160 / 480.There is 2 more located remote from substation
dick
			
				Last edited: 
			
		
	
								
								
									
	
		
			
		
		
	
	
	
		
			
		
		
	
								
							
							
				