wbalsam1
Senior Member
- Location
- Upper Jay, NY
Recently, an inspector in upstate New York state failed an inspection where the electrical contractor had installed a service of 600 amperes. It was just a pedestal service, no building, foundation or water main involved. Just a pair of ground rods 5/8" X 8'. The contractor installed #4 cu to the rods and when the inspector showed, he failed him and demanded that the contractor install something in the neighborhood of 1/0 cu to the rods.
What's up with this kind of thinking?
What's up with this kind of thinking?