blvengineers
Member
Hello. I am trying to size main feeder and branch feeders for a 4 story military dorm. Here is the distribution. Main service on 1st floor servers 10 individual panels separated by mechanical, lighting and general receptacle loads. On the 2nd, 3rd and 4th floors, there are large distribution panels that serve the same for each floor. Where do I start with diversifying the load? There are approximately 8 dorm units served from each general receptacle panel, about 20 units served from the mechanical panel and 44 from the lighting panels. Approximately the same for each floor. I am having issues understanding how to apply the diversity. For the record, there is no fixed cooking equipment.