knoppdude
Senior Member
- Location
- Sacramento,ca
Have a residential customer with a 200 amp panel, that has way too many circuits filling it, to the point that grounded conductors are being doubled and triple up on the terminal strip. What I am going to suggest to him is that he upsize the service to supply two 200 amp panels, and split up the circuitry. I have to do some load work on his house, but it is in need of more panel space, and this is the only way I can think of to accomplish this. Most of the wiring has been done by a handy man, so there are many problems beyond this, which I will bring to his attention as they are uncovered. Has anyone had experience doubling up on residential panels, and how did it work out?