what's 2meg.... 6k amps at 480 3phase..... roughly...
now, you want to know how many hours it takes to install a piece of heavy electrical equipment, but not doing any of the electrical work.
riggers don't need much assistance, and the ones i've worked with mainly want you to leave them alone.
so, are you gonna do anything besides broker the deal, and stand there while it's set? how long does that take?
there's a foot thick slab, and welding embedments, and ground spools, and chemical grounds, or a ground
grid, and cadwelds and conduits, like a couple dozen 4" from the genset to the ats, and from the ats to the
MSG, and a fuel tank, and testing and commissioning, and .....
and a load bank is absolutely necessary if you don't want to wet stack the diesel cycling it every week unloaded.
most of those are tiered 25% - 100% in stages..... there's a ton of stuff there in pipe, wire, and such.
none of that you want to know about... just how much time to put in for..... what?