when dealing with large(24x18) cast iron roadway boxes(1,500lbs and up) is most of the work done(setting in place) done with a crane? I'm thinking there is not much labor for the electrician. Well I guess he has to be there to assist.Thanks.
 

iwire

Moderator
Staff member
Location
Massachusetts
when dealing with large(24x18) cast iron roadway boxes(1,500lbs and up) is most of the work done(setting in place) done with a crane? I'm thinking there is not much labor for the electrician. Well I guess he has to be there to assist.Thanks.

We sub that work out to the site contractor if the specs did not already do so.
 