maghazadeh
Senior Member
- Location
- Campbell CA
Good Morning everyone,
We have this new commercial project consist of (27,000sq ft total) 2-story office building with a garage basement. Electrical room is in the basement w/ a post tension type floor between basement and 1st floor The full height of basement floor is even with grade level where incoming secondary utility ducts comes in to utility pull sect.. Plans call for a 1200A, 208/120V 3ph, 4w, 65K AIC, MSB. consist of U.P.S., Meter/main 1200A, (3) sects. totaling (15) 200A Meter/Main w/ 200A CB for future tenants, (1) 400A Meter/main as house-panel.
Since future tenant unknown, we are thinking to go with 200A pull-out fuse disco. instead of main CB. Reason if future tenant needs only 100A then they just put 100A fuse into 200A pull-out instead od replacing CB.
Q1.) Do you see any problem with fuse pull-out disco verses CB in regards to ground fault coordination.
For indoor MSB installation with underground service ducts, we come in from bottom of U.P.S. all open no sheet metal to punch for. I have not done this type of install where incoming utility ducts inters U.P.S. from the back wall- top sect. of uderground pull sect.
Q2.) Coming into U.P.S. from the back wall with (5) 5" PVC ducts,, do we need to punch the back wall sheet metal enclosure? or cut a big enough rectangle? or remove the back half-top sheet metal completely?
Thanks for any reply.
We have this new commercial project consist of (27,000sq ft total) 2-story office building with a garage basement. Electrical room is in the basement w/ a post tension type floor between basement and 1st floor The full height of basement floor is even with grade level where incoming secondary utility ducts comes in to utility pull sect.. Plans call for a 1200A, 208/120V 3ph, 4w, 65K AIC, MSB. consist of U.P.S., Meter/main 1200A, (3) sects. totaling (15) 200A Meter/Main w/ 200A CB for future tenants, (1) 400A Meter/main as house-panel.
Since future tenant unknown, we are thinking to go with 200A pull-out fuse disco. instead of main CB. Reason if future tenant needs only 100A then they just put 100A fuse into 200A pull-out instead od replacing CB.
Q1.) Do you see any problem with fuse pull-out disco verses CB in regards to ground fault coordination.
For indoor MSB installation with underground service ducts, we come in from bottom of U.P.S. all open no sheet metal to punch for. I have not done this type of install where incoming utility ducts inters U.P.S. from the back wall- top sect. of uderground pull sect.
Q2.) Coming into U.P.S. from the back wall with (5) 5" PVC ducts,, do we need to punch the back wall sheet metal enclosure? or cut a big enough rectangle? or remove the back half-top sheet metal completely?
Thanks for any reply.