?Point?-
In Jersey. I laid out a price sheet per point some 20 yrs ago, new work, old work.....new work eg: 15 amp recept., 20 amp recept., 3 way, 1pole switch,.....etc.... add in 15 a circuit at 60........... my per point was 28 to 35........circs at 60 and 70 for 20a (this was when 250' 12-2 rx was $28)..............
a builder had me work for 23 per point instead........ kinda broke even.
Reevaluated the sheet some 20 yrs. later........per point might be ~45-55.
For time you may what to figure what it would take you to drill and wire + 12' for a recept. plus the material (box,recpt.,reg or decora,cvr.plate.misc.) smokes 3 wire, box,smoke time to wire,, 3 ways more money on the device, 3 wire, more that 12 ft........kinda go through with all the wiring scenarios
and well wing it. Add the circuits in after the points at about 65' of wire to hit the first point, labor, breaker.............
Edit............don't forget about that afci nonsense...........at another $50 to your circuit breakers.
Kinda a educated guesstimate.
U
Good Luck.