mstrlucky74
Senior Member
- Location
- NJ
NECA recommends increasing the labor for working heights above 10'. Why is that? Does it increase install time whether working off a ladder or lift?
I am not sure why they set the bar at 10ft but they must have some data somewhere. The work time changes from an 8ft ladder to a 12 ft ladder myself i tend to slow down the higher I go just being mindful of fall hazard. If space and job permits a lift is always the way to go.
We just did a stage where we were 86' up and could look down through a ribbed floor and the men walked like they were walking steel! It slowed the job way down and you could not fall through, but sure felt unsafe to they men; plus not wanting to drop stuff that could fall 86' to the stage. I had walked the job before bidding and added 48 hrs. for it, as the men did get used to it after 3 days.
We just did a stage where we were 86' up and could look down through a ribbed floor and the men walked like they were walking steel! It slowed the job way down and you could not fall through, but sure felt unsafe to they men; plus not wanting to drop stuff that could fall 86' to the stage. I had walked the job before bidding and added 48 hrs. for it, as the men did get used to it after 3 days.
Just completed a job running MC in a ceiling height of 19' up to 35'. The guys were in a large scissor lift with nothing in the way, all open floor. It still took them 1 1/2 to 2 times longer to run the cable than if they were working off of the ground or 6 ft ladders. Some one posted once that for every 6 ft you need to double the time.
Just completed a job running MC in a ceiling height of 19' up to 35'. The guys were in a large scissor lift with nothing in the way, all open floor. It still took them 1 1/2 to 2 times longer to run the cable than if they were working off of the ground or 6 ft ladders. Some one posted once that for every 6 ft you need to double the time.