I need to bring 3 12/2 MC cables through a poured concrete floor is it sufficient to use 3 m fire stopping around cables? Or is a sleeve required. Plan does not show any diagrams with reference to electrical sleeves only plumbing.
	
		
			
		
		
	
				
			 
				