TrickleCharge
Member
- Location
- CA
There are 2 services. THe GEC comes in to one of them in to the ground buss bar (ufer ground). The second service is right next to the first and the EC ran the GEC for this from the service to the ground buss of the first service. Allowed? Does this go against 250.64(C)? I think ultimately the solution that is most commonly seen is an external ground bar that is used as a point of connection for all GEC to come in to but they did not do this. THanks