Rusin Electric
Member
- Location
- New Jersey
Hey, I'm installing a new 200 amp service (3 meter 3 panels) in the basement. In the picture below, the 2 existing panels would be replaced by 2 new ones and I'm going to try and squeeze my 3rd panel to the left of those 2. If you notice in the picture, there is a ledge to the left of those panels. Would an inspector give me a hard time about that? Or do you guys think I would be better off putting my 2 panels higher and putting the 3rd one below the other 2. Any feedback would be great! Thanks