In the services article,  it says the disconnection switch needs to be as close as to the point of entry as possible.  Would it be allowed to have a service end box which brings power to a utility C/T cabinet which then would bring power to a main disconnect switch?  I would think that the order would have to be service end box followed by disconnect switch followed by C/T cabinet (tapped ahead of switch).
	
		
			
		
		
	
				
			 
				
 
 
		