Rockyhamella
Member
- Location
- Maryland
Hi, I'm new to this site and I'm hoping to benefit from the knowledge of those more experienced then myself. I don't know if it's wishful thinking but if at all possible I'd like to hear from Mike Holt himself on this matter.
My Question is in regards to the Gas Bond on a Stand By Generator..?
This is a problem I've had with the plumbing side of inspections believe it or not and not the electrical. But for some reason (me) the electrical installer has to deal with the plumbing inspection.
Now I had some problems with several different county inspectors throughout the State of Maryland. I won't mention the county's as I don't want to create any issues there but some had a difference of opinion on how I bonded the gas.
I've tried several different ways to do the bond while trying to be as safe and cost effective as possible.
One of My questions is why bond the gas? Does it seem more dangerous to do so?
The fact that I have an equipment ground should be good enough I believe and am I adding an extra risk with a gas bond?
Isn't the gas already bonded at the main usually anyway if it's required?
Now for the how to bond...
Some Counties have made me grab the water Bond and run to the gas for the unit,
Some made me go from the Electrical Main.. Which I don't really agree with,
Some made me go from the Homes Main Gas Meter Bond,
Many of these brought up cost as the area of the generator could be over 50 to 100 foot away from these areas and we all know bare copper of # 6 can be expensive when you get long lengths of it.
Plus not to mention we're always told to make our grounding/bonding runs as short as possible.
And am I right or is A bond just supposed to be shortest possible jump from the closest Ground point available?
Here's one problem I have with bonding the gas.. I know it's pointless to drive a ground rod and bond the gas, which is how some of the counties would make me do it unit I continued to argue that its stupid. So isn't it the same thing if I bond it from the Water or Gas Main?
It is Useless?
So I finally came up with a way I think makes a little more sense and convinced most of these Counties to let me use it. I would just like to hear some feed back if its a good way or not to bond the gas. I'd really rather not bong the gas at all but at this point the plumbing wont pass without it.
So at one point they use to make me drive a ground rod and go from the ground rod to the back of the generator where a lug is installed by the generator manufacturer; and from there I had to go the point the gas was installed at the generator with a bond clamp.
What I am doing now; I go from this lug at the back of the generator; which I tested continuity from the equipment ground bar to this lug. And I go right to the Gas with a bond clamp. It's only 2 ft of bare # 6 compared to any other method and I believe in theory that it's more effective all around if you must bond/ground gas.
But I do still feel a little uneasy about this matter as safety is important to me.
Any opinions?
My Question is in regards to the Gas Bond on a Stand By Generator..?
This is a problem I've had with the plumbing side of inspections believe it or not and not the electrical. But for some reason (me) the electrical installer has to deal with the plumbing inspection.
Now I had some problems with several different county inspectors throughout the State of Maryland. I won't mention the county's as I don't want to create any issues there but some had a difference of opinion on how I bonded the gas.
I've tried several different ways to do the bond while trying to be as safe and cost effective as possible.
One of My questions is why bond the gas? Does it seem more dangerous to do so?
The fact that I have an equipment ground should be good enough I believe and am I adding an extra risk with a gas bond?
Isn't the gas already bonded at the main usually anyway if it's required?
Now for the how to bond...
Some Counties have made me grab the water Bond and run to the gas for the unit,
Some made me go from the Electrical Main.. Which I don't really agree with,
Some made me go from the Homes Main Gas Meter Bond,
Many of these brought up cost as the area of the generator could be over 50 to 100 foot away from these areas and we all know bare copper of # 6 can be expensive when you get long lengths of it.
Plus not to mention we're always told to make our grounding/bonding runs as short as possible.
And am I right or is A bond just supposed to be shortest possible jump from the closest Ground point available?
Here's one problem I have with bonding the gas.. I know it's pointless to drive a ground rod and bond the gas, which is how some of the counties would make me do it unit I continued to argue that its stupid. So isn't it the same thing if I bond it from the Water or Gas Main?
It is Useless?
So I finally came up with a way I think makes a little more sense and convinced most of these Counties to let me use it. I would just like to hear some feed back if its a good way or not to bond the gas. I'd really rather not bong the gas at all but at this point the plumbing wont pass without it.
So at one point they use to make me drive a ground rod and go from the ground rod to the back of the generator where a lug is installed by the generator manufacturer; and from there I had to go the point the gas was installed at the generator with a bond clamp.
What I am doing now; I go from this lug at the back of the generator; which I tested continuity from the equipment ground bar to this lug. And I go right to the Gas with a bond clamp. It's only 2 ft of bare # 6 compared to any other method and I believe in theory that it's more effective all around if you must bond/ground gas.
But I do still feel a little uneasy about this matter as safety is important to me.
Any opinions?