We have a project we are currently bidding on that has a large amount of Wiremold's " Designer Series" 4000 on it. We have done small portions of the older 4000 series but nothing in the DS. Overall the job isn't too technical, but I don't really have a good labor unit for installing. Does anyone have a rough idea on typical man hours to install it say per 10', or even per 100' assuming all of the work is about 8" above floor level, and we will be only doing the power side of the wiremold? Any input is greatly appreciated.