I believe what I'm looking at is a 3ph 480v Delta ungrounded service. The reason I question it is because I'm not familiar with the voltages I'm getting.
A-B 480v
B-C 480v
C-A 480v
to ground
A-G 480v
B-G 480v
C-G 6v
This is in the factory I just started working for, but hese voltages don't seem right.
I believe the C phase is shorted to ground. If so, is it possible for this to cause stray voltage onto the ground of another service in thie same facility. Are there any suggestions on how to isolate the ground-fault.
A-B 480v
B-C 480v
C-A 480v
to ground
A-G 480v
B-G 480v
C-G 6v
This is in the factory I just started working for, but hese voltages don't seem right.
I believe the C phase is shorted to ground. If so, is it possible for this to cause stray voltage onto the ground of another service in thie same facility. Are there any suggestions on how to isolate the ground-fault.