Can I downsize a neutral on a PV system? And where in the code can I find this? If I am connecting to a 120/208v system I have to run a neutral just for my production meter. I am told that the only reason the meter needs the neutral is for a reference point between phases and that there is no current on it. As long as it's a balanced system I should be able to downsize, correct?