Who determines what and when flexibility is required?
As an installer can't I determine I require a flexible raceway to make installation easier?
It strikes me you are trying to read it more restrictive then it is.![]()
517.30 Essential Electrical Systems for Hospitals.
(3) Mechanical Protection of the Emergency System.
(3) Listed flexible metal raceways and listed metal sheathed cable assemblies in any of the following:
d. Where necessary for flexible connection to equipment
Interesting question I was removed as the electrical inspector in a hospital remodel / addition, when the electrical contractor foreman made that exact same argument. The owner of the contractors company sat on the board for the hospital