HoosierSparky
Senior Plans Examiner, MEP
- Location
- Scottsdale AZ
- Occupation
- Senior Plans Examiner
I have an interesting situation. I have a company that leases a property with a building on it. They have purchased the property immediately next door and propose putting a building on it. They want to run power to a sub-panel on the new building from the leased building. This doesn't seem right, but I cannot find anything in the NEC. I have seen a section in the plumbing code that prevents this. I can't believe the NEC hasn't addressed this too. Suggestions? :?