I am currently running a conveyor project, includes one new carousel and reworking four existing systems. We were not provided a spec book until about mid-way through the project so we did not have one to bid off of. The only thing we had to go off in the beginning was a layout, number of motors, vfds, photo eyes, etc. Here's the problem I've run into, well series of problems.
We finished up the new carousel and the customer has been using it for three months without inspecting it. Turns out, the use of a few items are against spec (threadless rigid couplings and connectors, the use of beam clamps to hold equipment to the conveyor system, lengths of sealtite at a max of 3ft). Now we failed the Airport's inspection.
What, if any, leg do I have to stand on? Will I have to eat the cost of re-doing everything? If this falls into liquidated damages will I have to eat that cost as well?
I did find in the Specs where they were supposed to provide a layout of conduit runs and inspect them before I pulled wire or did any terminations. Which, they did not do.
Thanks for your help.
We finished up the new carousel and the customer has been using it for three months without inspecting it. Turns out, the use of a few items are against spec (threadless rigid couplings and connectors, the use of beam clamps to hold equipment to the conveyor system, lengths of sealtite at a max of 3ft). Now we failed the Airport's inspection.
What, if any, leg do I have to stand on? Will I have to eat the cost of re-doing everything? If this falls into liquidated damages will I have to eat that cost as well?
I did find in the Specs where they were supposed to provide a layout of conduit runs and inspect them before I pulled wire or did any terminations. Which, they did not do.