Hi All,
I've been poking around a while here and am intimidated by the wealth of knowledge. I'm posting only because I cannot find an answer I've been looking for so I need some help.
What are the grounding bonding requirements for a utility scale PV system when it comes to an over-ground cabling system like CAB other messenger wire based hangers? I'm based out of Canada but manage projects in the USA as well.
I'm an electrician here with a strong knowledge of the CEC and there is really nothing that dictates the need for grounding within the hangers. The system should be bonded at either end via termination points and the equipment should be bonded via the piles or grounding grid. Am I correct in assuming the same is true in the NEC?
Example:
Currently dealing with a system that requires 22 x 600mcm aluminum cables per hanger to be hung over-ground (landfiill, cant penetrate). Wondering if we need to run a separate ground within the CAB style hangers? I'm thinking we don't need it at all as the messenger wire is isolated from the cables and the cables will be terminated at each end into a box that's bonded to the grid.
Thoughts?
I've been poking around a while here and am intimidated by the wealth of knowledge. I'm posting only because I cannot find an answer I've been looking for so I need some help.
What are the grounding bonding requirements for a utility scale PV system when it comes to an over-ground cabling system like CAB other messenger wire based hangers? I'm based out of Canada but manage projects in the USA as well.
I'm an electrician here with a strong knowledge of the CEC and there is really nothing that dictates the need for grounding within the hangers. The system should be bonded at either end via termination points and the equipment should be bonded via the piles or grounding grid. Am I correct in assuming the same is true in the NEC?
Example:
Currently dealing with a system that requires 22 x 600mcm aluminum cables per hanger to be hung over-ground (landfiill, cant penetrate). Wondering if we need to run a separate ground within the CAB style hangers? I'm thinking we don't need it at all as the messenger wire is isolated from the cables and the cables will be terminated at each end into a box that's bonded to the grid.
Thoughts?