"Any idea that what could happeded?
Harmonics issue?
No fire resistant concrete walls between power transformers?
Sprinkler system was not operational?
No redundancy?
Others?
But the entire Heathrow was shot down for many hours.................We will never know with certainty what happened.
If they state unequivocally it was not terrorism there is at least a 1 in 3 chance it was. They can't very well admit it.
Or it could be bad design and/or defective parts. Or just bad luck.
My apologies........But the entire Heathrow was shot down for many hours.................
I agree - most of the time it is not. And failures do happen from to time. But this is not just a failure - it was a major disaster. A total shut shut down of one of the #largest airports in the world.Id be more interested in knowing their routine maintenance and inspection results. Mainly on the insulation testing and gas/liquid testing.
Most of the time it is nothing nefarious but instead decay or lack of maintenance. All things fail given enough time.
I agree - most of the time it is not. And failures do happen from to time. But this is not just a failure - it was a major disaster. A total shut shut down of one of the #largest airports in the world.
That transformer, yes. But the entire airport was shut down for two days !The shut down is a result of a design flaw. Fully redudant transformer adjacent with no blast wall. That means if the transformer fails catastrophically it will take out the one next to it.
That is the design flaw. The transformers being that close with no wall meant that all the terminations, wire, protection equipment, etc. needed to be tested and repaired before they could energize the redundant transformer or even install a spare. All of it was damaged by the single transformer's failure.That transformer, yes. But the entire airport was shut down for two days !
I'm sure that there is more to this. Look at this:That is the design flaw. The transformers being that close with no wall meant that all the terminations, wire, protection equipment, etc. needed to be tested and repaired before they could energize the redundant transformer or even install a spare. All of it was damaged by the single transformer's failure.
If it were me, I would probably due a single breaker - single bus at different ends of the airport and use a 33kv or 16kv intertie PMH system to pad mounted transformers or have a intertie feeder to each sub with an additional breaker.
Yes but airport are feeding by 3 substations. So redundancy were available. I saw some comments about 11 kV ring that is not available downstream.The shut down is a result of a design flaw. Fully redudant transformer adjacent with no blast wall. That means if the transformer fails catastrophically it will take out the one next to it.
I'm sure that there is more to this. Look at this:
"A fire near Heathrow Airport has caused commuter chaos as train services suffer significant delays early this morning.
National Rail has announced that disruption is expected until midday.
The operator announced on its website: "A fire next to the track between Heathrow Terminals and London Paddington means trains running between these stations may be delayed by up to 30 minutes"
For Heathrow it was 2 days. I'm sure there was more to it than that.
Only final report could indicate it.Id be more interested in knowing their routine maintenance and inspection results. Mainly on the insulation testing and gas/liquid testing.
Most of the time it is nothing nefarious but instead decay or lack of maintenance. All things fail given enough time.
Design flaw? Those are big words to use against a system that was working great for a long time.That is the design flaw. The transformers being that close with no wall meant that all the terminations, wire, protection equipment, etc. needed to be tested and repaired before they could energize the redundant transformer or even install a spare. All of it was damaged by the single transformer's failure.
If it were me, I would probably due a single breaker - single bus at different ends of the airport and use a 33kv or 16kv intertie PMH system to pad mounted transformers or have a intertie feeder to each sub with an additional breaker.
Design flaw? Those are big words to use against a system that was working great for a long time.
Maybe an installation failure? Also a big statement that isn't appropriate.
More than likely multiple things could have been done different if there were no limit to schedule, cost and schedule.
I dope they do.............Lets wait for preliminary report.
Only final report could indicate it.
The airport operations may be considered critical now that there was a failure, but I've worked on loads of critical projects that during design and construction the schedule and cost make the criticality questionable from the owner / operator's standpoint.I wouldn't know what else to call it. Something should always work well during normal operation. I would call the design incomplete if it didn't. It is how things fail that proves where the lack of follow through is. Especially in critical infrastructure.