  1. Re: any potential violation questions, if I'm not...

    Re: any potential violation questions, if I'm not mistaken, most all commercial workstations, at least in the US can only have up to 13 outlets on one circuit max. I did a spreadsheet a few years...
  2. Replies
    3$$
    Views
    1,022

    Did this not include the inductive motor current...

    Did this not include the inductive motor current for the cooling fan?

    Sent from my LGMP260 using Tapatalk
  3. Replies
    32$$
    Views
    1,746

    What a great conversation. I.e. The more you...

    What a great conversation. I.e. The more you know, the more you don't know!

    Sent from my LGMP260 using Tapatalk
  4. Replies
    32$$
    Views
    1,746

    Well if you're the one that's going to be there 5...

    Well if you're the one that's going to be there 5 years from now as mentioned by others I would make the case to do the upgrade and change the drawings although we know the customer doesn't always...
  5. Replies
    32$$
    Views
    1,746

    So if you have existing Breakers and existing...

    So if you have existing Breakers and existing feeders for the smaller Transformer and are considering putting in the 75, you would be required to put in the properly sized breaker and wire for the...
  6. Replies
    32$$
    Views
    1,746

    Here's a quick xref that covers the breaker...

    Here's a quick xref that covers the breaker sizing.

    When installing a transformer, use the transformer secondary rules in 240.21(C)(1) through (C)(6). 


    Where installed in accordance with one...
  7. Replies
    28$$
    Views
    1,491

    Correct, human design error, we had a MDF or IDF...

    Correct, human design error, we had a MDF or IDF closet where the electrical engineer put a 480/120/208vac 300 KVA xfmr adjacent side of this cable distribution closet within 2' where the magnetic...
  8. Replies
    28$$
    Views
    1,491

    Design choice, unless you have separate panels...

    Design choice, unless you have separate panels feeding the computer outlets with a Priority Generator Power or UPS circuit. We had 800+ workstations with three circuits, two normal, one or Computer...
  9. Replies
    51$$
    Views
    2,650

    Yes, totally agree, however, we had critical...

    Yes, totally agree, however, we had critical operations not only for the Datacenter but all 1750 people protected by one-ups circuit per office/per cubicle which included all energy management...
  10. Replies
    51$$
    Views
    2,650

    Sounds normal for totally unloaded, the property...

    Sounds normal for totally unloaded, the property I was referring to had a minimum running load 24/7 of 1000 KW. Data center load plus cooling. So the building was never unloaded. I'm sure with no...
  11. Replies
    51$$
    Views
    2,650

    I had a large property where the running loads on...

    I had a large property where the running loads on the building during the day with 1700+ people, started bringing down the voltage on the secondary side of our 16kv/480v 2500 KVA Xfmr. As far down as...
  12. Replies
    51$$
    Views
    2,650

    That's a long run, is this in a commercial area,...

    That's a long run, is this in a commercial area, large residential? It might be cheaper depending on the clients needs to install a new service entrance and pole mounted xfmr closer to the load. If...
  13. Replies
    5$$
    Views
    483

    Correct, per NEC 230.95 as quoted, The NEC...

    Correct, per NEC 230.95 as quoted,
    The NEC requires ground fault protection for 480/277V, 3-phase, 4-wire, wye-connected services rated 1,000A or more, but it’s optional in other configurations...
  14. Replies
    5$$
    Views
    483

    This should help answer some questions....

    This should help answer some questions. https://www.csemag.com/articles/choosing-between-3-pole-and-4-pole-transfer-switches/

    Sent from my LGMP260 using Tapatalk
  15. Replies
    25$$
    Views
    1,602

    Okay this thread might be getting a little old or...

    Okay this thread might be getting a little old or redundant but when you say you have three phase 240 volt on your primary and you want to feed a 3-phase 480 volt load how do you obtain that or am I...
  16. Replies
    25$$
    Views
    1,602

    It's just something I experienced adding new 200...

    It's just something I experienced adding new 200 KVA power distribution units to existing UPS systems critical output bus it was a standard that we used to pre energized on a non-critical 10000 day I...
  17. Replies
    25$$
    Views
    1,602

    There is always a load when you turn on any...

    There is always a load when you turn on any Transformer especially large ones depends on the level of saturation the Curve and the last time it was started up or energized so when connecting new...
  18. Replies
    9$$
    Views
    770

    It appears that they might have used the...

    It appears that they might have used the generator for 120volt loads, where the amps are up around 360+

    Sent from my LGMP260 using Tapatalk
  19. Replies
    9$$
    Views
    770

    Correct, a typical 3phase generator at 75 KVA or...

    Correct, a typical 3phase generator at 75 KVA or 60 KW is 208.4 amps @ three phase, the 400 amp breaker as you mentioned sounds like it was used for a special purpose like inrush current, but a 225 a...
  20. Replies
    9$$
    Views
    716

    You can calculate all you want, normally, I would...

    You can calculate all you want, normally, I would allways do a before and after for total load in amps. Knowing that heaters are normally a PF of 1, and the remaining unbalanced loads will also...
  21. Replies
    4$$
    Views
    389

    I've engineered a transfer inhibit switch on an...

    I've engineered a transfer inhibit switch on an ATS before, in my case, specifically, the ATS that was feeding the critical UPS and Battery systems including the maintenance bypass cabinet.

    I've...
  22. Replies
    16$$
    Views
    1,045

    When it's on a panel that's servicing critical...

    When it's on a panel that's servicing critical load with a main and sub main, all PDUs have 10AIC,

    Sent from my LGMP260 using Tapatalk
  23. Replies
    16$$
    Views
    1,045

    It is typical to have the Mains higher, regular...

    It is typical to have the Mains higher, regular load distribution breakers for power, 120/240 and 277 circuits at the 22k then critical distribution breakers inside let's say a PDU or UPS...
  24. Replies
    7$$
    Views
    731

    Assuming the air outlets are facing each other,...

    Assuming the air outlets are facing each other, I've seen the use of upward draft directional housings or addons. With drains and protective grates.

    If in or near a residential area, there could...
  25. Replies
    3$$
    Views
    655

    There are many variables with PF Cap maintenance...

    There are many variables with PF Cap maintenance and usually tied to the power supplied equipment, I.e. UPMs, Static UPS, where the choke transformer losses are suceptable to increases in...