    Coordination Study Requirement

    Does anyone know if inspector, plan reviewer really
    ask for project’s coordination study report / evident to review
    before they can pass the inspection...or this study’s
    just a requirement from code that we will need to meet.

  2. #2
    Join Date
    May 2008
    Location
    West Chester, PA
    Posts
    615
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Nobody has ever challenged one of my coordination studies.

    My experience is limited to my own conscience. Let your conscience be your guide. And remember there are only code rules for the emergency system.
    Alternate current
    Line to ground and ground to line
    Current alternates

  3. #3
    Join Date
    Feb 2003
    Location
    New York, 40.7514,-73.9925
    Posts
    4,717
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    I have only been asked to show a coordination study in one jurisdiction (NYC, between the first two levels at the service) and none other throughout the US, and I've done a lot in other jurisdictions.
    Ron

  4. #4
    Join Date
    Mar 2014
    Location
    South Florida
    Posts
    346
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    We are on a job where the contractor dragged their feet completing the study-still isn't done. The gear is ready to turn on. We aren't allowing them to energizing for anything other than testing until the study is approved. Somehow it's our fault??? That goes with the "let your conscious be your guide."

    Something tells me whomever did the study hasn't been paid yet.

  5. #5
    Join Date
    Feb 2014
    Location
    Charlotte, NC
    Posts
    393
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    That's a shame. We do these studies all the time and always ship the report before being paid; it's just how business is done. Even after I submit the report and invoice net-30, client usually drags their feet and pays at 30 days or a few days after.

    Think about it, what if contractors worked this way too? Nothing would ever get done unless everything was paid up front...

  6. #6
    Join Date
    Feb 2003
    Location
    Illinois
    Posts
    24,009
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Other than the few cases where the code requires selective coordination, I am not aware of any requirement to provide a coordination study.
    Don, Illinois
    (All code citations are 2017 unless otherwise noted)

  7. #7
    Join Date
    May 2007
    Location
    Westminster, MD
    Posts
    653
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quote Originally Posted by anbm View Post
    Does anyone know if inspector, plan reviewer really
    ask for project’s coordination study report / evident to review
    before they can pass the inspection...or this study’s
    just a requirement from code that we will need to meet.
    I think it all comes down to the specifications for the job. Was a Power System Fault, Coordination and Arc Flash Study called for? Since an electrical inspector is all about the NEC, I can see them asking for proof of compliance with 110.9 Interrupting Rating and 110.16(B) Service Equipment (labeling) Other than that I don't think an entire power study would ever be called out by an NEC inspector.

  8. #8
    Join Date
    Apr 2008
    Posts
    24
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Maybe he wants to see available short circuit current.