We have a disconnect that is bottom fed from the meter. For whatever reason the installer landed the meter sc on the load side of the disconnect and the feeders on the line side.
I can change out the meter conductors but the feeders will take some work.
Can the feeders be spliced in the disconnect.


Sent from my 0PM92 using Tapatalk
 

electricalist

Senior Member
Location
dallas tx
Is there a situation you couldn't. I'm debating it with a supervisor, he says you can't but has no reference.