    submittal

    Our lighting supplier requested : "I need breakdowns on the runs for Type C and Type D so I can provide all the necessary hardware". D are track lights. 4-150' of track with led heads and There are 4 rows of LED ribbon for C fixtures. I am assuming he wants to know how many coupling and connectors and ends he will need to add for hardware? I need a little lot of help.
    Last edited by charlie b; 05-22-19 at 03:50 PM. Reason: Fixed confusing spelling error in title.

  2. #2
    Join Date
    Feb 2003
    Location
    Seattle, WA
    Posts
    19,581
    Mentioned
    1 Post(s)
    Tagged
    0 Thread(s)
    Seems to me that your best move is to ask the supplier what he wants.
    Charles E. Beck, P.E., Seattle
    Comments based on 2017 NEC unless otherwise noted.

  3. #3
    Join Date
    Mar 2003
    Location
    New York
    Posts
    1,916
    Mentioned
    2 Post(s)
    Tagged
    0 Thread(s)
    Why isn't he looking at the print? Then you both count up and find out who is closer.