First post here, or I think it is.
In doing load calculations for a project, I was sent this in addition to the permanent building. It is meant as a temporary kitchen on site during construction for a 5 years project. My question is: If this is a prefab kitchen, and the manuf. says to provide the following connections (see below), do I apply Table 220.56? The manuf. did not include how many appliances or sizes...just connection. However, this is a larger kitchen with a lot of appliances. Do I calculate at 100%, assuming the kitchen manuf. has already taken demand?
From Vendor:
Connections for Large Kitchen:
● 2x400A 460V 3 phase
● 1x200A 208 3 Phase
Connection for Walk in Freezer:
● 1x100A 208 3 Phase
Connection for Walk in Cooler:
● 1x100A 208 3 Phase
Connection for Restroom/Changing Room
● 1x100A 120V 1 Phase
Thanks for the input
In doing load calculations for a project, I was sent this in addition to the permanent building. It is meant as a temporary kitchen on site during construction for a 5 years project. My question is: If this is a prefab kitchen, and the manuf. says to provide the following connections (see below), do I apply Table 220.56? The manuf. did not include how many appliances or sizes...just connection. However, this is a larger kitchen with a lot of appliances. Do I calculate at 100%, assuming the kitchen manuf. has already taken demand?
From Vendor:
Connections for Large Kitchen:
● 2x400A 460V 3 phase
● 1x200A 208 3 Phase
Connection for Walk in Freezer:
● 1x100A 208 3 Phase
Connection for Walk in Cooler:
● 1x100A 208 3 Phase
Connection for Restroom/Changing Room
● 1x100A 120V 1 Phase
Thanks for the input