Customer wants me to add 1 inlet feeding both of his 200 amp panels . Meter is outside and feeds these main breaker panels. I was going to split off from the inlet and feed 2 pole 30’s in the panels with interlocks. Reading around on old threads seems like this might be a code violation.
What’s the right way to do this? Break the neural/frame bond on the generator. Switched neutral Manual transfer switch?