pault587
Member
- Location
- Grand Rapids, MI
I have an application for a control panel that has a load of 480V 3 phase 436 amps. I am planning on using a 600 amp breaker to feed this panel. My question is if I want to use 350 kcmil 2 per phase do I use 3 conduits one for each phase or 2 conduits each phase in one conduit? The control panel spec says it can receive (2) 3in or (3) 2-1/2in conduit.
I was told yesterday that you must have each phase in a run. My electrician says that will be harder to run and wire.
Thanks in advance,
Paul