champion
Member
- Location
- St. Louis Missouri, US
Is it unusual for a utility company to not know which primary phase is A, B, C.
Primary line voltage in this project is 2400v.
The connection will be for 208v 3 ph service.
I noticed that the connection on the load side of the meter to the main disconnect is not the same.
Example---PHASE A = RED, PHASE B = YELLOW, PHASE C = BLUE ON THE LOAD SIDE OF THE METER.
These cables terminate on the disconnect as follows:
PHASE A = BLUE, PHASE B = YELLOW, PHASE C = RED.
Assuming that the utility company will connect the main transformers phase A, B and C to the appropriate cables as the meter is wired, I don't really have a problem.
When I asked the utility company to be sure and connect these phases to match the meter connections, they told me that they don't really know for sure which primary voltage is phase A, B AND C. They just connect them like they always do and nobody has any trouble.
I was thinking of getting my scope out and determine which phase is which for them but maybe its not just that necessary.
I was concerned about this a bit regarding the 3 ph A/C units installed on the roof of this building.
As far as load balancing on this project----I don't really think a big effect will be caused because of it, but I was shocked to hear what I heard.
Any input---
Thanks
Jim
Primary line voltage in this project is 2400v.
The connection will be for 208v 3 ph service.
I noticed that the connection on the load side of the meter to the main disconnect is not the same.
Example---PHASE A = RED, PHASE B = YELLOW, PHASE C = BLUE ON THE LOAD SIDE OF THE METER.
These cables terminate on the disconnect as follows:
PHASE A = BLUE, PHASE B = YELLOW, PHASE C = RED.
Assuming that the utility company will connect the main transformers phase A, B and C to the appropriate cables as the meter is wired, I don't really have a problem.
When I asked the utility company to be sure and connect these phases to match the meter connections, they told me that they don't really know for sure which primary voltage is phase A, B AND C. They just connect them like they always do and nobody has any trouble.
I was thinking of getting my scope out and determine which phase is which for them but maybe its not just that necessary.
I was concerned about this a bit regarding the 3 ph A/C units installed on the roof of this building.
As far as load balancing on this project----I don't really think a big effect will be caused because of it, but I was shocked to hear what I heard.
Any input---
Thanks
Jim
