I know that whe sizing the service to a group of motors you all the FLA of all the motors and then take 125% of the largest motor. Do you still need to take 125% of largest motor even if motors are not continuous?
Do you need to size conductors 125% for feeder to transformer or only 100% of transformer primary rated current? Is it good practice to size transformer feeders at 125% of transformer load? I have seen this done sometimes.
Do you need to size conductors 125% for feeder to transformer or only 100% of transformer primary rated current? Is it good practice to size transformer feeders at 125% of transformer load? I have seen this done sometimes.