Hi.
I have to feed a 1600A service through undergroungd feeders from utility secondary side.
Considering / applying temparture derating what size / type conductors ??????
(4) # 500 MCM , THWN PER PHASE OR,
(4)#600 MCM , THWN, PER PHASE ?????
TANX
I have to feed a 1600A service through undergroungd feeders from utility secondary side.
Considering / applying temparture derating what size / type conductors ??????
(4) # 500 MCM , THWN PER PHASE OR,
(4)#600 MCM , THWN, PER PHASE ?????
TANX