PSU Electrical
Member
- Location
- Bethlehem/Scranton
My mind is wondering with this one so bear with me:
I have a client doing a retrofit on a loading dock facility. The loading dock has an old Square D, 600A panelboard with practically no load on it, feed from a MDP a few hundred feet away. Of course, like every other client, they have no money and it needs to be done yesterday. Anways, they are in the process of putting a large APC Server in the office of this building that the other Engineering firm is demanding a 400A, 3-phase, 480V feed to the server. The 600A panelboard can only accept 225A breakers. I can not figure out a way to provide a 400A CB or Fused Disconnect to this server since the panelboard can only accept 225A breakers. So, my question is can (2) 225A CB's feed (1) 400A Fused Diconnect, then to the server? I would never suggest designing something like this but retrofits are terrible. The Electrician tells me there no real way to tap the 600A bus to add a 400A CB to it so that would leave me to think I either need to get a 400A feed from another building (very far away) or replace the 600A panel with a new 800A to accept 400A CB's. Any other suggestions?
I have a client doing a retrofit on a loading dock facility. The loading dock has an old Square D, 600A panelboard with practically no load on it, feed from a MDP a few hundred feet away. Of course, like every other client, they have no money and it needs to be done yesterday. Anways, they are in the process of putting a large APC Server in the office of this building that the other Engineering firm is demanding a 400A, 3-phase, 480V feed to the server. The 600A panelboard can only accept 225A breakers. I can not figure out a way to provide a 400A CB or Fused Disconnect to this server since the panelboard can only accept 225A breakers. So, my question is can (2) 225A CB's feed (1) 400A Fused Diconnect, then to the server? I would never suggest designing something like this but retrofits are terrible. The Electrician tells me there no real way to tap the 600A bus to add a 400A CB to it so that would leave me to think I either need to get a 400A feed from another building (very far away) or replace the 600A panel with a new 800A to accept 400A CB's. Any other suggestions?