I have 2 Main GE breakers (125amp) that need to tie into an EOP on the 7th floor and an existing EOP on the 1st in Fire Control Room. I have the existing EOP now tied into a raceway that connects to my New EOP on 7, and both of those also tie into the 2 UPS's with dry contacts. My question is how do I power my 7th floor EOP from my main without conflicting with the 1st floor existing eop? Or do I just tie into the existing?