Sorry I believe I've asked this before but will save responses for reference. Don't look at a lot of duct bank work.
Have about 700' of 2" RGS feeding 13 park poles. Will have 1 elbow at each pole(there's a box by the pole so it's not in/out) and then some out in the field. Tough to know the exact routing(pic below as example) but obviously there will be bends. What determines whether you would use factory elbow or bend? Thanks.
Have about 700' of 2" RGS feeding 13 park poles. Will have 1 elbow at each pole(there's a box by the pole so it's not in/out) and then some out in the field. Tough to know the exact routing(pic below as example) but obviously there will be bends. What determines whether you would use factory elbow or bend? Thanks.