WA_Sparky
Electrical Engineer
- Location
- Vancouver, WA, Clark
- Occupation
- Electrical Engineer
General question looking to see if the following is A. Code Compliant, and B. Possible issues.
For the given project we have an existing building (building 1), metered, and disconnect fed by an oversized transformer.
There will be a new building (building 2) 100' away (same owner).
Client said they need the existing transformer to feed (1) meter, to feed (1) ATS (both buildings will now be backed up by generator), the load terminal of the ATS is to feed a load break (acting as both service disconnects), and that feeds each building separately. If both building grounds are bonded, are there potential issues code or safety wise? I gathered from other posts 1 meter feeding 2 buildings is technically 2 services per NEC even though utility might view it as 1, since there is 1 meter charged.
Personally I would rather have 2 meters, 2 ATS's and keep everything separate but there is push back. Interested in hearing your thoughts.
For the given project we have an existing building (building 1), metered, and disconnect fed by an oversized transformer.
There will be a new building (building 2) 100' away (same owner).
Client said they need the existing transformer to feed (1) meter, to feed (1) ATS (both buildings will now be backed up by generator), the load terminal of the ATS is to feed a load break (acting as both service disconnects), and that feeds each building separately. If both building grounds are bonded, are there potential issues code or safety wise? I gathered from other posts 1 meter feeding 2 buildings is technically 2 services per NEC even though utility might view it as 1, since there is 1 meter charged.
Personally I would rather have 2 meters, 2 ATS's and keep everything separate but there is push back. Interested in hearing your thoughts.