hello-We are working on a tunnel project with a 20,000' long tunnel being mined by a tunnel boring machine. We are having grounding issues that are affecting various things in the tunnel, including the possibility of ground fault events. We have power stations every 1000'. We need to extend a grounded conductor the entire length from the switchgear (15kv). The ground actually has 29 amps on it. The voltage being run is 12.47k. I used a standard voltage drop calculation to figure the voltage drop and the wire size, but that really doesn't work because that is phase vd. Does anybody have any advice on how to run the ground using a correct voltage drop, etc. This is a new situation for us, and my engineer taksed me with figuring it out (good learning lession I guess). Grounding is not my strongest of areas. Any advice would be greatly appreciated.
Thanks-
Brace McGillivary
Electrical Designer
Thanks-
Brace McGillivary
Electrical Designer