I have been asked to construct a 200 amp underground service.
Just wanted to run this by some of you. This is the first time I've been asked to submit a plan.
I'm thinking that I would trench 18" and run 2" Schedule 80 with 3 4/0AL runs. The distance is about 250 ft. from transformer to meter base. There could be as many as two 90's and one 45.
Any other thoughts or considerations that have forgotten would be greatly appreciated.
Norb
Just wanted to run this by some of you. This is the first time I've been asked to submit a plan.
I'm thinking that I would trench 18" and run 2" Schedule 80 with 3 4/0AL runs. The distance is about 250 ft. from transformer to meter base. There could be as many as two 90's and one 45.
Any other thoughts or considerations that have forgotten would be greatly appreciated.
Norb