220.31(b)

Status
Not open for further replies.

wmeek

Senior Member
Location
Texas
Occupation
Electrician
Is it saying you can take all existing and all new loads at nameplate VA and take 8000 at 100% and the rest of other loads at 40%, and then add all your A/C or Heating loads whichever is the larger load for both existing and new loads at 100% to derive your Main Service Size. I just am trying to make sure I have this right and am doing the correct calculation for adding loads to an existing dwelling.

Thanks
 
Is there anyone who has applied this section for seeing if an existing service is adequate to support a new add on.
 