When using the Optional Calculation for dwelling units per 220.82, would it be permissible to use this same calculation when you have more than one panel? For example, if you had a main "MDP" Panel outside with (3) indoor panels serving various loads (ie. Panel A,B,C), can the calculation be used on each individual panel A,B,C to size their respective circuit breakers and feeders (or) would all the loads be required to be taken at 100% on panels A,B,C and then 220.82 would only apply to the main MDP for service feeder rating?
This is a friendly debate with a plans examiner whom is also a member of the forum.
Thanks!