220.87 and 555.12

Status
Not open for further replies.

charlie b

Moderator
Staff member
Location
Lockport, IL
Occupation
Semi-Retired Electrical Engineer
A marina wants to increase the loading at some of the slips (i.e., provide two 30 amp receptacles per boat instead of the existing one per boat). Do you think we can apply the 30 day metering process described in 220.87 to obtain the "existing load"? My reading of 555.12 does not give me a clear answer to this question.
 
Status
Not open for further replies.
Top