MazzEE
Member
- Location
- Atlanta, GA US
If I'm adding a load to an existing building, I understand the getting the peak demand from 1-year's worth of utility data or 30-day metering requirements to prove additional load(s) are acceptable, however with this new exception added in NEC 2020, what then happens when you add new load(s) to a building with PV (renewable energy system)?
The exception negates this method (which makes sense), but then what do you do? Take the output of the PV system and add it to the Calculated Loads as if designing from scratch, then add your new loads in? (I may be missing something, but any direction would close this loop I'm stuck in)
The exception negates this method (which makes sense), but then what do you do? Take the output of the PV system and add it to the Calculated Loads as if designing from scratch, then add your new loads in? (I may be missing something, but any direction would close this loop I'm stuck in)