- Location
- Lockport, IL
- Occupation
- Semi-Retired Electrical Engineer
Existing building, no new loads being added. Existing small generator provides power via existing ATS to optional standby loads. Plan is to replace the normal feeder to this ATS, thus delivering power from a different panel. Both existing "normal source" and new "normal source" are in the same building, and this is a small portion of the building's overall load. The task at hand is determining the feeder size for the new "normal source."
Question: Do I need to perform a feeder load calculation, or else take a 30 day load measurement, in order to confirm the existing load? I can certainly use 220.87, by taking the maximum measured demand over 30 days, add 25%, and then use the value of "zero" for the amount of new load. But do I have to go that far? Would a shorter measurement be acceptable (e.g., one week), just as a "sanity check," since this really isn't a load addition.
Question: Do I need to perform a feeder load calculation, or else take a 30 day load measurement, in order to confirm the existing load? I can certainly use 220.87, by taking the maximum measured demand over 30 days, add 25%, and then use the value of "zero" for the amount of new load. But do I have to go that far? Would a shorter measurement be acceptable (e.g., one week), just as a "sanity check," since this really isn't a load addition.